The average application process takes between 3 to 4 weeks, after submission of all relevant supporting documents in compliance with the Singapore Green Label criterion that the product falls under.
| Application | Application Fee | Validity |
| New application per product | S$3,500 | Two Years |
| Renewal application per product | S$2,300 | Two Years |
| Normal processing would take 3-4 weeks | ||
| Express processing fee for an application (3 working days):Additional S$1,000 on top of the application fee | ||
| Rapid processing fee for an application (7 working days):Additional S$500 on top of the application fees | ||
Please note the following:
- Payment will be required after the submission of the complete set of documents. Status of the completion of documents will be determined by the SGLS Secretariat.
- Assessment work will commence upon receipt of Application and first set of supporting documents.